| Financial Number: 443461-1-52-01   Project Length: 1.49 miles Project Limits: SR-9/I-95 To/From Park & Ride Bridge No. 860601, 860628, 860600, 860638 and SR-842 to NB SR-9/I-95 Bridge No. 860598 Projected Letting: May 2022 Start Date: Fall 2022 Completion Date:  Spring 2023 Estimated Construction Cost: $8.3 M Scope of Work:  
 
                    	Bridge painting with full removal and replacement of existing paint/coating on the existing steel bridge. 	Minor repairs to bridge drainage system. Construction Impacts: 
 
                    	Work will be done in phases to reduce the effects of construction on the community.	Occasional single lane closures during construction.	Two-way traffic and access to all property will be maintained at all times. Contact Information:
 |