State Road (SR) 93/I-75 Alligator Alley Resurfacing, Restoration, and Rehabilitation (RRR) Project – Section 2

Financial Numbers:444122-1-52-01

Project Length: 12.39 miles

Project Limits: Mile Post (MP) 31.261 to the Everglades Toll Plaza (MP 18.873)

Start Date: November 2024

Completion Date: Fall 2026

Contractor: Ranger Construction Industries, Inc.

Estimated Construction Cost: $24,576,002

Scope of Work:

The project improvements include milling and resurfacing the roadway within the project limits to ensure long-term resilience; replacing guardrail within the project limits to enhance safety for motorists; and upgrading signing and pavement markings within the project limits to enhance nighttime visibility.

Point of Contact:

Para información y preguntas en Español, por favor llame al (954) 777-4302.

 

Documents:

PDF Icon444122-1_Alligator Alley RRR_Project Flyer - December 2024.pdf

 

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

Pre Construction_Alligator Alley

During Construction

Alligator Alley Paved Roadway   November 2024Alligator Alley Paved Roadway_2   November 2024Compacting for Guardrail Mowing Strip   Dec. 2024Roadway Shoulder Paving   Dec. 2024
Guardrail Installation   January 2025Guardrail Installation_2   January 2025

 

Project Map


Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express
zero