State Road 845/Powerline Road Mobility Improvement Project from SR 870/Commercial Boulevard to NW 29th Street

Financial Number: 440746-3-52-01 & 441727-1-52-01

Project Length: 1.77-miles

Project Limits: Powerline Road from SR 870/Commercial Boulevard to NW 29th Street

Virtual Public Meeting:

Start Date: March 8, 2021

Completion Date: Early 2023

Contractor: Weekley Asphalt Paving, Inc.

Estimated Construction Cost: $3.1 million

Scope of Work:

Work consists of repurposing the existing outside travel lanes from Commercial Boulevard to West Oakland Park Boulevard to accommodate 7-foot buffered bicycle lanes in each direction and repurposing the outside lanes from West Oakland Park Boulevard to NW 29th Street to accommodate 4-foot bicycle lanes in each direction. Improvements also include installing 4-foot raised landscaped islands in each direction, milling and resurfacing, and installing landscaping and irrigation.

Point of Contact:

 

Contact Information:

Documents:

PDF IconPowerline Road Mobility Improvement Project

 

Project Photos

Pre-Construction

Click to view enlarged version/details

During Construction

Click to view enlarged version/details
 
 



Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express